Please check back often.  As new information becomes available this website will change.

June 7, 2017 Drone Footage of Building Project.

Thank you for taking the time to check out this webpage, where you can get all of the latest information regarding the new Building Project.  Below you will find several updates from Allen Van Driel, CEO at SCMH.  Please check back often to learn new details.

VISIBLE PROGRESS - Update from the CEO (June 2017)

Probably the two most commonly heard questions about the construction for our replacement hospital, at least until very recently, have been “Are they way behind schedule because of all the rain?” and “Is that a pond out there, or what is that big hole?” But within the last week or so, more commonly heard is “Wow, I guess they really are getting started”.

As everyone around here knows, it has, indeed, been a very wet spring. Generally, that’s good news for farmers trying to raise a crop (unless it gets too wet to allow planting). And, overall, it’s good news for our project as well. Since dirt work for the project began the middle of March, there have been a total of six days when weather and wet ground prevented work on the site. We’ve measured about 10.3 inches of rain in that time period at the site, so only losing six days of productivity is actually pretty good. The Construction Superintendent told us last week that although we are a few days behind the short-term schedule they planned with the subcontractors, they do not anticipate an overall project delay. That means that the weather delay days they had built into the schedule have been adequate for the weather we’ve had. I want to take just a moment to thank Hutton Construction for the excellent job they’re doing so far with the planning, coordinating, and supervising the project. They’ve been good to work with from our perspective, and the Hospital Board members who have attended construction progress meetings have been very impressed with Hutton’s organization and adaptability to keep the project moving.

Because we know that the community is interested in progress of the project, we want to make information available as readily as possible. To that end, we have arranged with Hutton to have photos of the site made available to us to share with the public on a regular basis. If you follow us on our Facebook page, you may have already seen some photos posted there last week, I’m including some of the photos here as well to show the progress. These photos are from a drone “flyover” conducted by Doug Armknecht last week.

0525Still1 (002).jpg

In this first photo, which was shot from the north end of the project near Highway 36, the footings for part of the inpatient care wing of the hospital are visible to the left side. On the right side of the photo the pad and steel framework of the portion of the building that will house Maintenance and Mechanical rooms, Purchasing and Storeroom, and Environmental Services are visible. To the south of the outline of the hospital building, the construction office and equipment staging trailers are visible. Also visible in the top right corner of the photo is the construction access road entering the site from East Kansas Street.

The second photo was shot from above Hubbard Stadium looking northeast. In the foreground are visible the edge of the athletic facilities. The construction office is in the lower right corner of the photo. In the upper center Jones Machinery is visible in the background. The footings that were quite visible in the first photo are not as visible in this view, but the concrete pad and steel structure are clearly visible to the left end. In the upper left end of the photo is the “pond” referred to earlier. This is actually a “borrow pit”, where dirt has been excavated for purposes of filling and leveling the site where the actual construction is occurring. Before the project is finished, as grading and leveling of other parts of the site occur, this borrow pit will be filled in, and won’t be present when the project is complete.

We will continue to share photos of the site and the building as construction progresses. One important point I need to make before I conclude relates to public safety. One of the most important considerations throughout the construction project is the safety of workers and anyone visiting the site. There are currently about 45 workers on site each day, and a number of pieces of heavy equipment moving around the site. The ground is very rough, partly due to the rain, and partly due to the nature of construction sites. Hutton Construction asked us to remind the public that the entire area is a restricted access area at all times. Anyone on the site must have permission to be there, and must have protective clothing, including high visibility outerwear and hard hats. Although we know this is an exciting time for the community as construction progresses, PLEASE do not enter the site to get a closer look. To do so would be dangerous, regardless of the time of day. We thank the public for your cooperation. Stay tuned for regular updates from us to show progress.

ALL TOGETHER, NOW. DIG! - Update from the CEO (March 2017)

We were pleased with the turnout for our ceremonial groundbreaking last Thursday. As I had jokingly predicted, the weather turned out much more seasonal than it had been (though not as cold or wet as the next day)! You gotta love springtime in the Midwest. Nearly 80 degrees on Wednesday, and about 40 degrees colder with a stiff northeast breeze on Thursday. So if any of the folks in thepictures look chilled, it’s because it was COLD.

The first picture shows the members of the Hospital Board of Trustees with the County Commissioners. To my left in the picture are Hospital Trustees Jim Sweat and Bruce Hardacre, County CommissionersArt Befort and Tom James, Hospital Trustees Kenton Weltmer and Bret Strine, and County Commissioner Roger Allen. Hospital Board member Dr. Joe Barnes was out of town and unable to join us.

The second picture shows the Public Building Commission Board of Directors with the County Commissioners. From the left are PBC Boardmembers John George, Ron Rahjes, Burke Phelps, and Gary Jepson, along with County Commissioners Art Befort, Tom James, and Roger Allen. PBC Board member Ron Griffith was out of town and unable to join us.

The third picture shows members of the Medical Staff and Hospital leadership team. From the left are Tammy Windscheffel, APRN, Dr. Leah Wiehl, Dr. Hannah Haack, Dr. Stacey Dimitt, Dr. Ferrill Conant, CFO Viola Babcock, Chief Nursing Officer Sarah Ragsdale, and me. We’re all smiling, but you can see the effect of the wind on hairdos. Mine looked as good as ever. Dr. Justin Overmiller was out of town and unable to join us for the ceremony. We were pleased that Dr. Wiehl, who will join Smith County Family Practice in August, was in town and joined us for the event.

After the cold photo op, we all adjourned to the Srader Center, where it was MUCH warmer. There we enjoyed cookies and drinks while we discussed the plans for the new facility with those in attendance. We thank all who joined us. If you were unable to be present for the event, the plans for the new facility will soon be on display in the hospital lobby. Actual construction on the new building will begin in about two weeks, and is expected to continue for about 18 months. I’ll continue to share details of the construction progress periodically. As construction begins, it is important to point out that for safety reasons the area will be fenced and will be a true “hard hat area”. Visitors will be allowedinto the site only by arrangement while       construction is underway. We do expect, though to be able to share photos, some taken by drone, from the site to show construction progress. Stay tuned – we’re underway!

 

HAPPY NEW YEAR! - Update from the CEO (January 2017)


      As 2016 drew to a close, we made major strides in regards to two projects that have been discussed in these blogs previously.

     First was our conversion to a new electronic health record. As planned, we “went live” with our new system at midnight on December 5. Overall, we’re finding the new Cerner system to be a much better system than the one we were previously using. As I mentioned in an earlier communication, the ability to have one medical record to encompass all care provided at the clinic and the hospital is a HUGE advantage, one that will streamline many processes. Of course, all of our physicians, nurses, and other clinical staff had to get used to the new system. Despite the fact that it is overall a better system, just learning where to find things in a new system takes time, so each of them has struggled at times. But with the passage of more than three weeks since go live, it gets a little better each day. Several of the providers have commented that once we get information about each patient populated into the new system, it is clear that this system will be much more user-friendly than what we were using before. We believe and hope that the improved functionality in the new system will translate into a better patient experience for each of you. However, we are still in the transition period, so I continue to ask for patience when you present for care at either the clinic or hospital. Plan to arrive a few minutes before your scheduled appointment and PLEASE remember to bring your insurance card with you.


     The second project with major developments is our building project for the replacement facility. Several milestones were reached in regard to this project. First was that workers for Smith County Roads department began removal of some trees around the property. This is the first step in constructing an access road into the building site from the south (from East Kansas Street or 165 Road, whichever designation you prefer). This access road will provide a route for construction equipment and trucks to enter the site during the construction phase without disrupting traffic flow on Highway 36. This access road will be a rock road, and will provide access to the completed hospital from the south. It is our hope that this road will eventually be hard surfaced, but the cost of that is not in our initial budget. In addition to the work on access to the site, we have achieved another major hurdle. In December we received from Hutton Construction their Guaranteed Maximum Price (GMP) for the project. Because our contract with Hutton is what is termed a Construction Management at Risk arrangement, any cost overruns that are not a result of approved change orders will be borne by the contractor. We were very pleased to find that the GMP kept uswithin the initial budget for the project. Having the GMP means that some of the subcontracts for the project can be put out to bid. Hutton Construction has initiated this process for subcontracts for dirt work at the site and for concrete for the building slab. Other contracts will follow at appropriate intervals. The GMP could only be delivered to us because we are certain enough of the final design for the project that Hutton can be comfortable that costs will not change substantially.  Accompanying this article is the latest architect rendering of the exterior of the building. Each step along the way helps us move theproject towards completion. We are EXTREMELY excited about this, and hope you are as well.

     As we tear the page off of the calendar and realize that the old year is finished and a whole new year lies ahead, I want to wish each of you the very best of success during 2017.  And I hope you share the same optimism and excitement that we feel as we enter a new year. It promises to be a very exciting year, filled with progress and new developments.

 

WHY HAVEN’T WE STARTED YET? - Update From the CEO (October 2016)

I know most people in the community are anxiously awaiting visible signs of construction at the site of the new Smith County Memorial Hospital. I hear many questions about the project. “When will we break ground?” “Why haven’t they started working yet?” “Is there a problem?” “Have they hit a snag?” Allow me to take a few moments to update the status and answer some of your questions.

We, like many of you, had initially hoped that we would be ready to break ground and “move some dirt” this fall. However, for a variety of reasons, we have known since earlier this summer that the time line had been pushed back. This was partly because of the care we took in arranging the project financing through issuance of revenue bonds by the Public Building Commission, and obtaining commitment from the USDA for long-term financing of the project. It also was partly due to conditions in the construction industry. Like us, many other organizations (hospitals, schools, businesses) decided that the availability of record-low financing made it a good time to undertake construction projects. The result was that the architects and construction contractors have been inundated with projects competing for their time and talents. The method being used for the project calls for the construction management firm (Hutton Construction) to deliver a Guaranteed Maximum Price to us before construction work can begin. What this Guaranteed Maximum Price means is that based on our agreement regarding the building plans, Hutton will determine the price. After that GMP is delivered to us, any cost over-runs are the responsibility of the Construction Manager (unless they are a result of change orders we agree to). Once Hutton has delivered the GMP, they will begin issuing requests for bids for various portions of the building project. These include (but certainly will not be limited to) site preparation (dirt work), plumbing work (much of which will be installed below the concrete), preparation and pouring of the concrete slab, procurement and erection of the structural steel, installation of wall studs, sheetrock, ceilings, flooring, electrical components, and many, many other parts of the project.

At the present time, we expect the GMP to be delivered to us during the second half of November. With that time line, and following preparation of bid documents, requesting of bids, and hiring of some subcontractors, we will be ready to begin work. The current timeline calls for a groundbreaking in February, with initiation of serious construction work in March. The construction timeline allows for up to 18 months for actual construction, although that may change based on weather, availability of materials, availability of workers, and many other factors. So our present time line is to have construction completed during the third quarter of 2018.

For those who have heard (or maybe shared) the idea that there are problems with the project and it will not go forward, I want to reassure you that this is completely false. Construction funding in the form of revenue bonds have been sold, and funds are being drawn as needed to pay building expenses. At this point, those expenses are mostly architect fees and a few minor expenses necessary to validate the status of the plans (this includes geotechnical engineering, or soil boring services). The architects have spent hundreds of hours working on plans. Some of that time has been in Smith Center meeting with myself, with the Board, the Medical Staff, and with key staff members to assure that the plans are drawn the way we want them.  In addition, much more of the architects’ time has been spent in their offices, drawing plans and specifications based on our discussions. So while we understand the anticipation, and perhaps anxiety, that people in the community are feeling, rest assured that the building project is moving forward at an appropriate pace. I’m sure the community will be even more excited when there are more visible signs that construction is underway. In the meantime, please enjoy the anticipation as we work to make sure the project is done right and on time. As always, if you have questions about the project, we invite you to submit them through our project website – www.scmhfuture.org

Building Project Progresses - Update From the CEO (July 2016)

It seems like everywhere I go, people ask me “How’s the hospital building project coming along?” In the blog I wrote two months ago, I mentioned a lot of behind the scenes activity going on in relation to the hospital building project. We are excited becausealthough there is still not a lot of visible activity on the new site, there definitely have been important milestones reached this month.

One of those important milestones was closing the sale of the property for the new facility. The photo that accompanies this article shows the closingtransaction taking place. Kenton Weltmer and Bruce Hardacre, representing the Smith County Memorial Hospital Board of Trustees, and Gayle and Kristi Jones, the sellers of the property are shown with   Karen Panter of Collier Abstract and Title on June 17. The site, as mentioned previously, is located south of Highway 36 and east of the current Orscheln building.  This means it is directly east of the Smith Center High School.

Pictured from left to right: Gayle and Kristi Jones, sellers of the land; Karen Panter, Collier Abstract and Title; Bruce Hardacre, Hospital Board Treasurer and Kenton Weltmer, Hospital Board Chairman.

Pictured from left to right: Gayle and Kristi Jones, sellers of the land; Karen Panter, Collier Abstract and Title; Bruce Hardacre, Hospital Board Treasurer and Kenton Weltmer, Hospital Board Chairman.

Another milestone achieved this month involved financing for the building project. On June 29 the Smith County Public Building Commission issued revenue bonds to provide the construction financing for the project. Piper Jaffray & Company were the Bond Underwriters for the transaction. They were able to negotiate the terms of the arrangement so that we can draw funds from the available amount when we need them, rather than receiving the whole amount at once. The advantage of this arrangement is that we don’t pay interest on the money until we draw it from the available funds. This will save us a considerable amount of money over the term of    construction.

The third milestone achieved this month was receiving notification from the US Department of    Agriculture that our application for a Rural Development Loan was approved. This loan will provide long term financing for the project once    construction is complete. I mentioned during the Town Hall meetings held earlier this year that part of our financing strategy is to use the USDA financing to provide long term financing (the term of the loan is 35 years) at a very low interest rate. The Public Building Commission and the Board of trustees will meet with USDA representatives next week to receive the letter of commitment for the loan. The extra good news that we received in conjunction with the notice of approval is that the USDA long term interest rate will drop again effective July 1. The unprecedented interest rate of 2.75% is the highest interest we will be required to pay for the loan. If the interest rate should happen to be lower than the 2.75% rate at the time construction is complete and USDA disburses funds, we will get that lower interest rate. But the rate cannot be higher than the current rate. I mentioned in my last blog that the decrease in interest rates since we did our financial projections would save us considerable money over the term of the loan. This further drop makes the savings greater.

The architects and construction manager are continuing to work on final designs and site plans for the building. When they are more final, we will share them. Stay tuned to this website for developments. As always, if you have specific questions about the project, you may feel free to submit them through the website as well.

Please enjoy a safe harvest season!

 

WHERE DO WE GO FROM HERE? - Update from the CEO (April 2016)

Last month we announced the results of the advisory referendum regarding the hospital building project.  With results showing that 80% of the voters are in favor of the project, it seems to most folks like we should be making progress to get started.  Hardly a day goes by, and absolutely not a week goes by, that we don't have someone ask what the next steps are and when we will begin to see visible signs of progress.  So, here's a brief update as of the first week in April.

Shortly after the votes were counted, The County Commissioners, the Public Building Commission Board of Directors, and the Smith County Memorial Hospital Board of Trustees met to begin the legal process for the financing.  Each Board passed a resolution that, taken together, will provide the legal basis for the financing.  The PBC Board published the legal notices in the newspaper that are required for them to issue bonds.  The three Boards met with a representative from Piper Jaffray, the company that will underwrite the bonds.  Piper Jaffray is publishing, with our assistance, information about the building project for banks who might be interested in participating in the bond issuance.  When that information is complete, the underwriters will request proposals for the bond issuance.  The proposals they receive will be reviewed competitively, and an award will be made to the firm with the best proposal.

While the financing process is underway, several other things are in process simultaneously.  The purchase of the land for the building project is being finalized.  The boundaries of the property have been surveyed to provide a legal description for the recording of the sale.  Meanwhile, the architect and the construction management firm have been working on schedules for completing building designs and construction timelines.  These are not final yet, but significant discussion has been held.  Discussions have begun with the Kansas Department of Transportation about the location of access roads to the property.  Work was finalized by an independent auditing and accounting firm on projected financial statements in support of our loan application to the U.S. Department of Agriculture.  This loan would provide long term, low interest rate financing for the project.  The bonds that the PBC Board will issue will provide the short term financing for construction.  Last week we received the welcome news from the USDA that the interest rate on their long term loans dropped, effective April 1, to 2.875%.  This unprecedented rate, which is 3/8% below the rate when our loan projections were constructed, will save us approximately $2.5 million over the repayment term of the loan.  So, while we hoped that we would have a commitment from the USDA by the end of March, the slight delay actually worked in our favor.

What does all of this mean?  Is means that while you can't see visible signs of construction in progress yet, there is actually a lot of activity underway behind the scenes.  All of this behind the scenes work is necessary to set the stage for us to actually begin construction.  We hope by this time next month that we will know more details about bidding and construction schedules.  As information becomes clear to us, we will certainly share it with the public.  It is very clear that the public is interested in what is happening.  As details develop, the best way to stay up to date is to follow our progress on this website.  

That's where we are for now.  If you have specific questions, feel free to ask in person, or you can submit them via this website as well.

Check out our Q&A page here to learn more.

 

Town Hall Meeting Smith Center Ks, January 27th, 2016

If you don't have time to dig through the facts and you want to ask a specific question you can call us at 785-282-6845 ext 203, email us at development@smithcohosp.org or contact us by clicking the button below.

Design subject to change

Design subject to change

Design subject to change